THE
CONNECTICUT LIGHT & POWER
CO. v. PUBLIC UTILITIES REGULATORY AUTHORITY et al., SC 21123
Judicial
District of New Britain
Administrative
Appeal; Rate Setting Pursuant to General Statutes § 16-19e; Interpretation of
Settlement Agreement; Whether Settlement Agreement Provides for Recovery of
Storm Related Costs as "Core Capital Projects." In
2018, the plaintiff, The Connecticut Light and Power Company, doing business as
Eversource Energy (Eversource), sought to amend its electric distribution
rates. Around that same time, Eversource incurred costs related to storm
damage. Eversource and the defendant, the Public Utilities Regulatory Authority
(PURA), entered into a 2018 settlement agreement to resolve the rate case. That
agreement provided that Eversource, after spending a certain amount on capital
projects, could recover through its base electric rates the cost of improving
certain infrastructure that was part of a "core capital program." The
agreement further provided that Eversource could recover storm costs incurred
after December 16, 2016, either during the next rate review or earlier, if
Eversource initiated a separate contested case. Eversource initiated a
contested case to recover those costs but failed to seek review of over $17
million in capital costs that it presumed would be recovered through the base
rate adjustment under the 2018 settlement agreement. PURA disallowed those
costs and rejected Eversource's claim after finding that the storm costs
"did not constitute core capital additions" under the 2018 settlement
agreement. In support of its argument that those costs were recoverable, Eversource
relied on a footnote in the settlement agreement referencing certain expert
testimony that Eversource claims supports its position that the storm costs can
be recovered as part of the "core capital program." The trial court disagreed,
dismissed Eversource's appeal in part, and remanded the matter to PURA. The
court concluded that "PURA has the discretion" under General Statutes
§ 16-19e, which pertains to rate setting, "to resolve this matter as it
has done" and, moreover, that "there is substantial evidence to
sustain PURA's final decision." The court remanded the case to PURA with
respect to the appropriate interest rate for certain charges, and Eversource
appealed to the Appellate Court (223 Conn. App. 136). That court dismissed Eversource's
appeal for lack of a final judgment, and, on remand, PURA issued a supplemental
decision regarding the interest rate. Eversource withdrew the remaining count
of its complaint, appealed again to the Appellate Court, and the Supreme Court
transferred this appeal to itself pursuant to General Statutes § 51-199 (c).
Eversource argues that PURA "ignore[ed] the plain language of the
contractual terms" and "did not have discretion to violate the
settlement agreement," which it maintains allows for the recovery of these
storm related costs. Eversource contends that the parties specifically had anticipated the recovery of "storm related capital
work" in the settlement agreement and that a proper interpretation of that
agreement, which Eversource asserts is plain and unambiguous, leads to the same
conclusion. Moreover, Eversource highlights that "PURA never found [that] any of the storm related capital projects
[were] imprudent."